Earlier this week I wrote on my Facebook page informing residents that I had written to Countryside about the traffic management and asked if they could do anything to offer residents some respite from the current traffic congestion that is caused, partially, by the works on the new spine road for Wolsey Park.
Today I have received a response from their comms team which offers a little (not all lot) in the way of how they will handle traffic management from 3rd September.
Let me know your thoughts in the comments below.
Dear Councillor Newport
I write, on behalf of Countryside Properties, to you in your capacity as a Downhall and Rawreth Ward member, regarding the traffic management measures currently in place on Rawreth Lane, Rayleigh.
As outlined in our last development update to the local community, issued in July, work is currently being undertaken on Rawreth Lane to create a new access junction into the Wolsey Park site. Countryside is making every effort to carry out and complete the work as quickly as possible.
Due to the nature of these works, some disruption is unfortunately unavoidable whilst the new access is created. Countryside however recognises and appreciates the patience shown by both local residents and road users whilst these works are carried out.
The works on Rawreth Lane are being undertaken in accordance with the permit issued by Essex Country Council, as the local highways authority, and Countryside is doing everything possible to minimise any impact.
Since the works began, the traffic signals have been manually controlled by operatives at all times and the works have been phased so that the lights are removed as often as possible, for example over weekends. In order to help further minimise disruption for local residents, additional measures have now been introduced (as of 3rd September), with restrictions in place to ensure the temporary traffic lights are only used outside of peak hours (between approximately 9am and 4pm).
The main phase of work is expected to be finished during October at which time the traffic management measures will be removed from their current location on Rawreth Lane.
There will be some additional works undertaken on Rawreth Lane during October, outside of the current working area, to install the gas supply into the site. This work, which is being carried out by the gas distributor rather than Countryside, will require some traffic management measures. This work is expected to last for two weeks and Countryside has encouraged Essex Country Council to request that the mitigation measures outlined above are implemented.
Countryside is aware that some other highways works are currently being carried out in the local area, such as on Watery Lane and London Road, however these are entirely unrelated to the Countryside works.
I hope that you find this information helpful. However, should you have any questions or require any further information, please do not hesitate to contact me.
Kind regards
Charles Bushe
Received on 5th September 2019
In the space of a few months, fortunes have changed for many and it could be about to get a whole lot worse. I’ve been saying for some time that our Councils need to more proactive in helping and promoting our High Street before it’s too late. The reality is, High Streets are on the
Read More
I have always been passionate about retail and being an entrepreneur and I suppose being born into a family of entrepreneurs it would be inevitable that it would become a passion of mine. So I recently attended a ‘workshop on the future of Rayleigh Town Centre’ which was organised by the District Council and the
Read More
Some of the play areas around Rochford District have been closed due to Health & Safety. Full announcement is available on the RDC website here
Read More